Mind Voyage × Oakley
RX Project Hub
Enter access code to continue
Mind Voyage × Oakley
Last updated — Active
Mind Voyage × Oakley
Tap to identify
Click on any section to leave a comment
RX Adaptation Track
Oakley RX Project
Mind Voyage × Oakley US × Oakley Milan
Hard Deadline
July 30, 2026
business days left
Backstop
Mid-August
Track A delivery Jul 30 · Track B (SF_ + HDO_) Aug 13 hard deadline
Brief
The Oakley RX track is a prescription eyewear adaptation of the Foundational Technologies campaign — five CGI statics translating the main campaign machines into RX context. Same protopian aesthetic, same translucent machinery language. The key creative challenge: black frames, clear lenses — no Prizm color.
Deliverable Status View all →
Loading assets...
Business days to deadline
Today
↯ Jul 30
Active
Blocked
Deferred
Next Milestone
First Internal Review
Week of Jul 28, 2026
UO_ + OM_ + PLU_ · R03 confirmed today · Frame.io notes due EOD · Delivery Jul 30
Action Required
+ comment
Open Items
Loading...
Recent Activity All →
Loading...
Upcoming Timeline →
Loading...
Latest Updates
Loading...
Docs & Files All →
Loading...
Comments
Loading...
Timeline Snapshot Full →
Task Jul 9Jul 16Jul 23Jul 30Aug 6Aug 13
Track A — Frame-Swap Assets (UO_ · OM_ · PLU_)
A1 → A2 → A3R01→R02→Final Review
A1 Done
A2 Done
A3 Today
Track B — New-Build Assets (SF_ · HDO Original · HDO New)
B0 → B1 → B2Direction→Concept→Refined
B0 Done
B1 Done
B2 Today
B3 Near-Final
B4 QC
Visual Timeline
Project Timeline
June — August 2026 · Click any milestone to update
Gantt Overview
Task / AssetJun 23Jun 30Jul 7Jul 14Jul 21Jul 28Aug 4Aug 11
Kickoff & Setup
RX KickoffMV + XK + Oakley Milan
Jun 24 ✓
CAD Files + RefsMarta → XK
Awaiting
Active — UO_ / OM_ / PLU_
UO_ Unobtainium
Building
Production
Review
OM_ O Matter
Parallel
Production
Review
PLU_ Plutonite
Production
Review
Legal Track — SF_ Shield Fusion
SF_ Legal Call
⚠ Target
SF_ Production
Blocked
Blocked
If cleared
Production
Deferred — HDO_ / Final
HDO_ Layout
Deferred
Deferred
Deferred
Start
Production
↯ HARD DEADLINE
Live Milestones
Click to update
Loading milestones...
Decision Log
Weekly Meetings
Key decisions — click any meeting to comment
Loading meetings...
Document Database
Docs & Files
Briefs · Recaps · References · Shared Links
Loading files...
Project Contacts
The Team
Mind Voyage · XK Studio · Oakley US · Oakley Milan
Mind Voyage — Creative Studio
Renato Braga
Creative Director / Founder
Mind Voyage
Primary creative lead. Client relationship and vendor leadership.
Matt Winkel
Executive Producer
Mind Voyage
Production, scheduling, budget, SOW. Coordinating first review meeting.
XK Studio — CGI Partner
XK Studio
CGI Vendor Partner
XK Studio
Primary CGI partner building all RX assets. Contact: yanika@xk.studio
Oakley US — Primary Client
Chasen Marshall
US Creative Client Lead
Oakley US
Primary Oakley creative contact. All creative alignment goes through Chasen.
Erin McInnis
Marketing Client Lead
Oakley US
Product direction, colorway, copy approvals.
Christy Lange
Project Manager
Oakley US
Oakley Milan — RX Track
Marta Ferrari
US Creative Client Lead
Oakley Milan
Primary RX contact. All RX files, CAD, colorway, etch refs, SF legal call flow through Marta. Offline mid-August.
Marco Cassanmagnago
US Marketing Lead Collaborator
Oakley Milan
Milan collaborator. Attends reviews.
All Deliverables
Project Deliverables
Click any asset to see its dedicated page — brief, decisions, files, comments
UO_Active
Unobtainium
Hex Jector
Black RX frame with clear lens replacing the original Prizm-tinted version. Machine, environment, and composition remain...
3 blockers
OM_Active
O Matter
Bat Flip
Parallel track to Unobtainium. Same black RX frame with clear lens swap applied to the Bat Flip machine. Runs concurrent...
2 blockers
PLU_Active
Plutonite
Hex Jector
Frame swap and clear lens adaptation for the Plutonite machine. Composition and environment entirely unchanged from main...
2 blockers
SF_Blocked
Shield Fusion
Legal Hold
The most complex RX asset. Requires Figma concept explorations and alignment before any production rendering begins at X...
3 blockers
HDO_Deferred
HDO Composite
V-Formation Layout
A composite layout bringing all five RX assets together in a V-formation composition. Visually the most ambitious of the...
2 blockers
UO_ Active
Unobtainium Hex Jector
Update status: ▶ Frame.io
📋
Brief
Black RX frame with clear lens replacing the original Prizm-tinted version. Machine, environment, and composition remain entirely unchanged from the main campaign version. The frame swap is the adaptation — not a redesign.
Creative Challenge
Making a clear lens visually striking without Prizm color doing the work. The clear lens must feel intentional and premium, not like an unfinished render.
Action Required
!
CAD files + 360° product images from Marta Ferrari (blocking)
!
Lens etch "O" mark references from Marta (blocking)
!
Final colorway direction from Oakley
Latest File
Add or update file link
+ comment
What We Deliver
  • 16:9 master — black RX frame, clear lens, environment preserved
  • 9:16 master — same treatment
  • TIFF + CMYK (300 DPI minimum) per master
  • RGB digital export per master
  • InDesign open file with copy, fonts embedded, layers named
  • Etched "O" mark on bottom-left lens per Marta's references
+ comment
📌
Key Decisions
RX Kickoff — June 24, 2026
Clear-lens solve identified as highest creative priority unlock for the entire RX track — must be solved before other assets can be judged
RX Kickoff — June 24, 2026
Two variants for first review: black-frame version + colored-frame alternative (electric blue)
RX Kickoff — June 24, 2026
Etched "O" mark applied bottom-left lens — reads as manufacturing detail, not added branding
RX Kickoff — June 24, 2026
CAD files + 360° product images required from Marta before production can begin
RX Kickoff — June 24, 2026
Composition, copy, and environment: unchanged from main campaign
RX Kickoff — June 24, 2026
Final colorway direction from Oakley — black confirmed as base, electric blue as alternative
Timeline Position
UO_ — UnobtainiumJun 23Jun 30Jul 7Jul 14Jul 21Jul 28Aug 4Aug 11
UnobtainiumHex Jector
Building
Production
Review
💬
Comments on this asset
Loading...
OM_ Active
O Matter Bat Flip
Update status: ▶ Frame.io
📋
Brief
Parallel track to Unobtainium. Same black RX frame with clear lens swap applied to the Bat Flip machine. Runs concurrently with UO_ — can leverage the same clear-lens solve once it's confirmed. Composition, environment, and copy unchanged.
Creative Challenge
Parallel workflow requires same creative solve as UO_ but machine geometry is different — clear lens interaction with the Bat Flip structure needs individual attention.
Action Required
!
CAD files + Bat Flip colorway links from Marta (blocking)
!
UO_ clear-lens solve must be confirmed first (dependency)
Latest File
Add or update file link
+ comment
What We Deliver
  • 16:9 master — black RX frame, clear lens, environment preserved
  • 9:16 master — same treatment
  • TIFF + CMYK (300 DPI minimum) per master
  • RGB digital export per master
  • InDesign open file with copy, fonts embedded, layers named
  • Etched "O" mark on bottom-left lens per Marta's references
+ comment
📌
Key Decisions
RX Kickoff — June 24, 2026
Parallel workflow to UO_ — can leverage same clear-lens solve once UO_ approach is approved
RX Kickoff — June 24, 2026
Colorway links for Bat Flip incoming from Marta — Bat Flip and Hex Jector options including electric blue
RX Kickoff — June 24, 2026
CAD files required from Marta before production start
RX Kickoff — June 24, 2026
Clear-lens solve must be confirmed on UO_ first, then applied to OM_
Timeline Position
OM_ — O MatterJun 23Jun 30Jul 7Jul 14Jul 21Jul 28Aug 4Aug 11
O MatterBat Flip
Parallel
Production
Review
💬
Comments on this asset
Loading...
PLU_ Active
Plutonite Hex Jector
Update status: ▶ Frame.io
📋
Brief
Frame swap and clear lens adaptation for the Plutonite machine. Composition and environment entirely unchanged from main campaign version. Copy unchanged. More straightforward frame swap than UO_ or OM_ due to machine geometry.
Creative Challenge
Ensuring the clear-lens approach solved on UO_ translates well to Plutonite's different machine structure and lighting environment.
Action Required
!
CAD files from Marta (blocking)
!
UO_ clear-lens solve must be confirmed first (dependency)
Latest File
Add or update file link
+ comment
What We Deliver
  • 16:9 master — black RX frame, clear lens, environment preserved
  • 9:16 master — same treatment
  • TIFF + CMYK (300 DPI minimum) per master
  • RGB digital export per master
  • InDesign open file with copy, fonts embedded, layers named
  • Etched "O" mark on bottom-left lens per Marta's references
+ comment
📌
Key Decisions
RX Kickoff — June 24, 2026
Begins after UO_ clear-lens solve is confirmed — can then run in parallel
RX Kickoff — June 24, 2026
CAD files required from Marta
RX Kickoff — June 24, 2026
Copy unchanged from main campaign Plutonite version
Timeline Position
PLU_ — PlutoniteJun 23Jun 30Jul 7Jul 14Jul 21Jul 28Aug 4Aug 11
PlutoniteActive
Production
Review
💬
Comments on this asset
Loading...
SF_ Blocked
Shield Fusion Legal Hold
Update status: ▶ Frame.io
📋
Brief
The most complex RX asset. Requires Figma concept explorations and alignment before any production rendering begins at XK. Legally blocked: the lamination process depiction has not been cleared by Oakley legal. Cannot proceed on any aspect until Marta's call with Limus and Alex resolves.
Creative Challenge
Two-layer block: (1) legal clearance on lamination depiction, (2) creative complexity requiring Figma alignment before any production work. Most resource-intensive of the five assets.
Action Required
!
⚠ Legal clearance from Marta / Limus / Alex — critical path (blocking everything)
!
Figma concept explorations (pending legal clearance)
!
Explicit go-signal from Renato to Lukas required before production start
Latest File
Add or update file link
+ comment
What We Deliver
  • Figma concept explorations (client alignment required before production)
  • 16:9 master — pending legal + Figma approval
  • 9:16 master — same
  • TIFF + CMYK exports per master
  • RGB digital exports
  • InDesign open file with copy, fonts embedded
+ comment
📌
Key Decisions
RX Kickoff — June 24, 2026
BLOCKED — lamination process depiction not cleared by Oakley legal
RX Kickoff — June 24, 2026
Cannot begin any creative work — not even Figma explorations — until legal clearance received
RX Kickoff — June 24, 2026
Marta to coordinate legal call with Limus + Alex + product team. Target: early July
RX Kickoff — June 24, 2026
Renato sends explicit green light to Lukas when legal clearance confirmed
RX Kickoff — June 24, 2026
Figma concept explorations must be approved by Marta and Renato before any production rendering at XK
RX Kickoff — June 24, 2026
Most complex asset — requires dedicated timeline once unblocked
Timeline Position
SF_ — Shield FusionJun 23Jun 30Jul 7Jul 14Jul 21Jul 28Aug 4Aug 11
Shield FusionLegal Hold
Blocked
Blocked
If cleared
Production
💬
Comments on this asset
Loading...
HDO_ Deferred
HDO Composite V-Formation Layout
Update status: ▶ Frame.io
📋
Brief
A composite layout bringing all five RX assets together in a V-formation composition. Visually the most ambitious of the five — requires all individual assets to be finalized first so their visual footprints can be balanced in the composite. Deferred until Shield Fusion visual direction is confirmed.
Creative Challenge
Cannot finalize V-formation visual balance without knowing Shield Fusion's visual footprint. The composite depends on how SF_ is solved — lens treatment, machine scale, and negative space all affect the composition.
Action Required
!
Shield Fusion (SF_) visual direction must be locked first
!
Shield Fusion legal clearance is therefore the root blocker for this asset too
Latest File
Add or update file link
+ comment
What We Deliver
  • V-formation composite layout — all 5 RX assets in one composition
  • 16:9 master — deferred
  • 9:16 master — deferred
  • TIFF + CMYK exports per master
  • RGB digital exports
  • InDesign open file with copy, fonts embedded
+ comment
📌
Key Decisions
RX Kickoff — June 24, 2026
Deferred until Shield Fusion visual direction is locked
RX Kickoff — June 24, 2026
V-formation layout balance requires Shield Fusion footprint to be confirmed first
RX Kickoff — June 24, 2026
Begins immediately after Shield Fusion visual direction confirmed — no further approvals needed
RX Kickoff — June 24, 2026
Will require dedicated sprint once SF_ unblocked — likely July production window
Timeline Position
HDO_ — HDO CompositeJun 23Jun 30Jul 7Jul 14Jul 21Jul 28Aug 4Aug 11
HDO CompositeV-Formation Layout
Deferred
Deferred
Deferred
Start if SF
Production
💬
Comments on this asset
Loading...
Pending Actions
Open Items
Grouped by owner — click any item to resolve
Loading open items...
Admin · Oakley RX Hub
Admin Access
Enter your 4-digit PIN to continue
Asset Status
Open Items
Current Open Items (click to resolve)
  • Loading…
Timeline Milestones
  • Loading…
  • Meeting Recap Links
    Update the Google Doc link for the RX Kickoff recap.
    Link saves directly to Supabase — visible to all users immediately.
    Add File / Link
    Delete Comments